Discount rate in the construction industry
[edit] What is the discount rate?
The New Rules of Measurement (NRM) are published by the Royal Institute of Chartered Surveyors (RICS). They provide a standard set of measurement rules for estimating, cost planning, procurement and whole-life costing for construction projects.
NRM3: Order of cost estimating and cost planning for building maintenance works, defines a ‘discount rate’ as:
|
The percentage rate required to calculate the present value of a future cash flow (i.e. used for bringing future costs to a comparable time base). For example, if investing at 3 per cent interest, then the present value is discounted by 3 per cent as it is worth less than future earnings due to interest. The discount rate is a factor or rate reflecting the time value of money that is used to convert cash flows occurring at different times to a common time base. |
Where the present value is:
'...the cost or benefit in the future discounted back to some base date, usually the present day, at a given compound interest rate'.
NRM3 defines the ‘treasury discount rate’ as:
'…the rate specified as the discount rate by the UK Government Treasury to be used as the discount rate for public sector whole life costing calculations.'
[edit] Other definitions
Guide to developing the project business case, Better business cases: for better outcomes, published by HM Treasury in 2018, defines the discount rate as: ‘The annual percentage rate at which the present value of a £, or other unit of account, is reduced over time. This is applied to values that are at constant prices and has nothing to do with currency inflation.'
Life Cycle Costing (BG 67/2016), written by David Churcher and Peter Tse and published by BSRIA in March 2016, defines the discount rate as: ‘The percentage by which costs or benefits occurring one year in the future are deemed to be less valuable than costs or benefits today. In life cycle costing, the discount rate is the difference between the cost of capital and the inflation rate. For public sector projects, the discount rate is 3.5% per annum. Discount rates can be expressed using different time periods (such as months) provided the study period is expressed in a consistent manner.’
ICMS: Global Consistency in Presenting Construction Life Cycle Costs and Carbon Emissions, 3rd edition, November 2021, published by the ICMS (International Cost Management Standard) Coalition, defines discount rate as a: ‘Factor or rate reflecting the time value of money that is used to convert cash flows occurring at different times (ISO 15686-5).’
[edit] Related articles on Designing Buildings
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
The heritage of nuclear and conventional power stations.
New measures to stop people being ripped off
Government to protect families from cowboy builders and aggressive bailiffs.
New Futurebuild showcase brings an innovation-first approach.
National Planning Policy Framework
Understanding the 2026 changes.
ECA's public affairs priorities
Member consultation opens to shape priorities for 2027 to 2030.
Dutyholder responsibilities from 1 July 2026.
Where performance meets practice
The Building Envelope Stage at UKCW Birmingham.
CIAT publishes briefing on planning reforms.
Leaders in Learning for Practice Network
Call for conservation leaders in learning to register interest in new network.
The importance of early engagement
Construction lessons from the Trillium HealthWorks Experience Centre.
Mayors are to be given planning call in powers
Mayors across England will be able to make the most important planning decisions.
The Master Builder: William Butterfield and his times. Book review.


















Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.